Week of February 3:
- Continue installation of spray on fireproofing nearing completion on Floor 6 and roof areas.
- Continue installation of overhead mechanical/plumbing on Floors 1–4, and starting Floor 5.
- Continue installation of hollow metal steel framing on Floors 3–4.
- Continue installation of exterior metal stud framing for building envelop.
- Excavate and install underground chilled water pipe service to building.
- Continue installation of final stair and pour concrete in all existing stair towers.
- Continue to erect scaffolding and begin installation of exterior sheathing on south and east sides of building.
- Building glass delivered to storage area near Ángel Cabrera Global Center (formerly Mason Global Center).
Week of February 10:
- Offsite work is progressing on coordination and inspections of pre-fabricated electrical rooms that are being fabricated offsite in a warehouse facility in southern Virginia. Floor 6 rooms delivered to site this week for installation.
- Continue installation of spray on fireproofing nearing completion on Floor 6 and roof areas.
- Continue installation of overhead mechanical/plumbing on Floors 1–5.
- Continue installation of hollow metal steel framing on Floors 3–4.
- Continue installation of exterior metal stud framing for building envelop.
- Excavate and install underground chilled water pipe service to building.
- Continue installation of final stair and pour concrete in all existing stair towers.
- Continue to erect scaffolding and begin installation of exterior sheathing on south and east sides of building.
- Completion of glass delivery to storage area near Ángel Cabrera Global Center (formerly Mason Global Center).
Utility Infrastructure Project
Week of February 3:
- Install striping on Wilkins Plaza for truck access during Phase 5 work (from David King Hall to Enterprise Hall, east of Johnson Center).
- Install temporary asphalt sidewalk areas on west side of Exploratory Hall.
- Begin installation of gabion wall at future Wilkins Plaza area.
- Complete work on new concrete site walls in Phase 3 areas (Wilkins Plaza east extension).
- Continue earthwork and grading to prep for framing and installation of new concrete sub slab/paver base in Phase 3 areas. Concrete under slab prep work to begin in Phase 3 area.
- Continue trenching, pipe installation, and backfill in Phase 4 areas (Central Heating and Cooling Plant south toward Presidents Park). Increased activity for the next several weeks in the area directly southwest of Central Heating and Cooling Plant.
- Continue backfill and site restoration in Phase 4 areas between Southside and Central Heating and Cooling Plant area along Rivanna River Lane.
- Intermittent closures will be required to complete restoration of areas where pipe installation is complete over next several weeks.
- Continue site restoration and concrete walk repairs in the area of Rivanna River Lane and Patriot Circle.
- Continue trench excavation in Phase 5 areas (East Plaza between Johnson Center and David King and Enterprise halls.
Week of February 10:
- Continue installation of gabion wall at future Wilkins Plaza area.
- Continue earthwork and grading to prep for framing and installation of new concrete sub slab/paver base in Phase 3 areas (Wilkins Plaza extension east). Concrete under slab prep work to continue in Phase 3 areas.
- Continue trenching, pipe installation, and backfill in Phase 4 areas (Central Heating and Cooling Plant south toward Presidents Park). Increased activity for the next several weeks in the area directly southwest of Central Heating and Cooling Plant.
- Continue backfill and site restoration in Phase 4 areas between Southside and Central Heating and Cooling Plant area along Rivanna River Lane.
- Intermittent closures will be required to complete restoration of areas where pipe installation is complete over next several weeks.
- Continue site restoration and concrete walk repairs in the area of Rivanna River Lane and Patriot Circle.
- Continue trench excavation and pipe installation in Phase 5 areas (East Plaza between Johnson Center and David King and Enterprise halls.