Robinson Hall Replacement
Week of December 16:
- Offsite work is progressing on coordination and inspections of prefabricated electrical rooms that are being fabricated offsite in a warehouse facility in southern Virginia. Additional rooms delivered to site this week for installation.
- Installation of site utilities, including storm sewer and telecom duct bank. In addition, below-grade waterproofing will be completed over the next two weeks.
- Prep for concrete slab on deck pour, Floor 6, north section.
- Continue installation of spray-on fireproofing.
- Continue installation of overhead mechanical/plumbing on Floors 1, 2 and 3.
- Continue installation of hollow metal steel framing on Floors 3 and 4.
- Continue installation of exterior metal stud framing for building envelop.
- Continue installation of materials on building mock-up.
Week of December 23:
- Offsite work is progressing on coordination and inspections of prefabricated electrical rooms that are being fabricated offsite in a warehouse facility in southern Virginia. Additional rooms delivered to site this week for installation.
- Installation of site utilities, including storm sewer and telecom duct bank.
- Prep for concrete slab on deck pour for roof.
- Start installation of material hoist.
- Continue installation of spray-on fireproofing.
- Continue installation of overhead mechanical/plumbing on Floors 1, 2 and 3.
- Continue installation of hollow metal steel framing on Floors 3 and 4.
- Continue installation of exterior metal stud framing for building envelop.
- Continue installation of materials on building mock-up.
Week of December 30:
- Offsite work is progressing on coordination and inspections of prefabricated electrical rooms that are being fabricated offsite in a warehouse facility in southern Virginia. Additional rooms delivered to site this week for installation.
- Installation of site utilities including storm sewer and telecom duct bank.
- Continue installation of material hoist.
- Continue installation of spray-on fireproofing.
- Continue installation of overhead mechanical/plumbing on Floors 1, 2 and 3.
- Continue installation of hollow metal steel framing on Floors 3 and 4.
- Continue installation of exterior metal stud framing for building envelop and begin installation of exterior sheathing.
- Continue installation of materials on building mock-up.
Week of January 6, 2020:
- Offsite work is progressing on coordination and inspections of prefabricated electrical rooms that are being fabricated offsite in a warehouse facility in southern Virginia. Additional rooms delivered to site this week for installation.
- Installation of site utilities, including storm sewer and telecom duct bank.
- Continue installation of material hoist.
- Continue installation of spray-on fireproofing.
- Continue installation of overhead mechanical/plumbing on Floors 1, 2 and 3.
- Continue installation of hollow metal steel framing on Floors 3 and 4.
- Continue installation of exterior metal stud framing for building envelop and begin installation of exterior sheathing.
- Complete installation of materials on building mock-up and begin relocation of fence panels to expose the mock-up panels to northeast corner of site.
Utility Infrastructure Project
Week of December 16:
- Continue installation of underground electrical and telecom for future Wilkins Plaza event power, light poles, and Wi-Fi.
- Continue work on new concrete site walls in Phase 3 area (Wilkins Plaza, east extension).
- Continue earthwork and grading to prep for framing and installation of new concrete sub slab/paver base in Phase 3 areas.
- Pipe delivery continues for Phase 4 areas (Southside east to Central Heating and Cooling Plant).
- Continue trenching, pipe installation, and backfill in Phase 4 areas; increased activity for the next several weeks in the area directly east of Southside as work continues on installation of a new underground chilled water pipe manifold. Testing and inspection of newly installed manifold.
- Rivanna River Lane remains open to one-way traffic, though intermittent closures may be required to complete testing and site restoration over next several weeks until phase of work is fully complete.
- Continue site restoration and concrete walk repairs in the area of Rivanna River Lane and Patriot Circle.
Week of December 23:
- Continue installation of underground electrical and telecom for future Wilkins Plaza event power, light poles, and Wi-Fi.
- Continue work on new concrete site walls in Phase 3 area (Wilkins Plaza, east extension).
- Continue earthwork and grading to prep for framing and installation of new concrete sub slab/paver base in Phase 3 areas.
- Continue trenching, pipe installation, and backfill in Phase 4 areas (Southside east to Central Heating and Cooling Plant); increased activity for the next several weeks in the area directly east of Southside.
- Clean out trenching and tie in at south loop chilled water takeoff point. Insulate chilled water caps and flow fill existing chilled water pipes to be abandoned in place.
- Remove existing chilled water piping at plant, install new chilled water piping, and tie into existing plant chilled water risers.
- Rivanna River Lane closes to traffic during winter break to help facilitate construction activities. The road will be restored to one-way traffic by the start of spring 2020 semester.
- Continue site restoration and concrete walk repairs in the area of Rivanna River Lane and Patriot Circle.
- Begin installation of fencing, erosion, and sediment control measures in Phase 5 areas (East Plaza between the Johnson Center and David King Hall, and down to Enterprise Hall).
Week of December 30:
- Continue installation of underground electrical and telecom for future Wilkins Plaza event power, light poles, and Wi-Fi
- Continue work on new concrete site walls in Phase 3 area (Wilkins Plaza, east extension).
- Continue earthwork and grading to prep for framing and installation of new concrete sub slab/paver base in Phase 3 areas.
- Continue trenching, pipe installation, and backfill in Phase 4 areas (Southside east to Central Heating and Cooling Plant); increased activity for the next several weeks in the area directly east of Southside Dining.
- Clean out trenching and tie in at south loop chilled water takeoff point. Insulate chilled water caps and flow fill existing chilled water pipes to be abandoned in place.
- Remove existing chilled water piping at plant, install new chilled water piping, and tie into existing plant chilled water risers.
- Rivanna River Lane closes to traffic during winter break to help facilitate construction activities. The road will be restored to one-way traffic by the start of spring 2020 semester.
- Continue site restoration and concrete walk repairs in the area of Rivanna River Lane and Patriot Circle.
- Continue installation of fencing, erosion, and sediment control measures in Phase 5 areas (East Plaza between the Johnson Center and David King Hall, and down to Enterprise Hall).
- Begin vacuum excavation test pitting to locate known utilities on Wilkins Plaza.
Week of January 6, 2020:
- Continue installation of underground electrical and telecom for future Wilkins Plaza event power, light poles, and Wi-Fi.
- Continue work on new concrete site walls in Phase 3 area (Wilkins Plaza, east extension.
- Continue earthwork and grading to prep for framing and installation of new concrete sub slab/paver base in Phase 3 areas.
- Continue trenching, pipe installation and backfill in Phase 4 areas (Southside east to Central Heating and Cooling Plant); increased activity for the next several weeks in the area directly east of Southside.
- Clean out trenching and tie in at south loop chilled water takeoff point. Insulate chilled water caps and flow fill existing chilled water pipes to be abandoned in place.
- Remove existing chilled water piping at plant, install new chilled water piping, and tie into existing plant chilled water risers.
- Rivanna River Lane closes to traffic during winter break to help facilitate construction activities. The road will be restored to one-way traffic by the start of spring 2020 semester.
- Continue site restoration and concrete walk repairs in the area of Rivanna River Lane and Patriot Circle.
- Continue installation of fencing, erosion and sediment control measures in Phase 5 areas (East Plaza between Johnson Center and David King Hall, and down to Enterprise Hall).
- Continue vacuum excavation test pitting to locate known utilities on Wilkins Plaza.