Robinson Hall Replacement
Week of October 21:
- Continue steel erection moving south and then up to roof and repeat starting at north end of building.
- Offsite work is progressing on coordination and inspections of prefabricated electrical rooms that are being fabricated offsite in a warehouse facility in southern Virginia.
- Continue installation of elevated underfloor mechanical and electrical and telecom utilities.
- Continue installation of brick on building elevation mock up.
- Continue installation of underground utilities on north and south ends of new building.
- Start layout of partitions on floor 3.
- Start spray on fireproofing on floor 1.
Week of October 28:
- Continue steel erection moving south and then up to clerestory starting at north end of building.
- Offsite work is progressing on coordination and inspections of pre-fabricated electrical rooms that are being fabricated offsite in a warehouse facility in southern Virginia.
- Continue installation of elevated underfloor mechanical and electrical and telecom utilities.
- Complete installation of brick on building elevation mock up.
- Continue installation of underground utilities on north and south ends of new building.
- Start layout of partitions on floor 4.
- Continue spray on fireproofing floors 1 and 2.
Utility Infrastructure Project
Week of October 21:
- Continue to excavate for new underground electrical and telecom for future Wilkins Plaza event power, light poles, and Wi-Fi.
- Continue work on new concrete serpentine wall in Phase 3 (Wilkins Plaza east extension) area.
- Pipe delivery continues for Phase 4 (Southside east to Central Heating and Cooling Plant) areas.
- Continue trenching and pipe installation in Phase 4 areas.
- Closure of Rivanna River Road as pipe is delivered and installed in Phase 4 areas. This closure will continue through early November. This work has been delayed a due to unforeseen underground conditions and pipe manufacturing problems.
Week of October 28:
- Continue to excavate for new underground electrical and telecom for future Wilkins Plaza event power, light poles, and Wi-Fi.
- Continue work on new concrete serpentine wall in Phase 3 (Wilkins Plaza east extension) area.
- Pipe delivery continues for Phase 4 (Southside east to Central Heating and Cooling Plant) areas.
- Continue trenching and pipe installation in Phase 4 areas.
- Closure of Rivanna River Road as pipe is delivered and installed in Phase 4 areas. This closure will continue through early November. This work has been delayed due to unforeseen underground conditions and pipe manufacturing problems.