Robinson Hall Replacement
Week of June 3:
- Continue excavation for foundations and underground mechanical work.
- Continue to pour concrete at new building foundations.
- Begin waterproofing of new foundation walls.
- Continue landscape and hardscape restoration of site around Harris Theatre.
- Commissioning and training for new mechanical equipment in Harris Theatre service/utility area.
- Procurement of materials for full-scale building envelop mock up.
Week of June 10:
- Continue excavation for foundations and underground mechanical work.
- Continue to pour concrete at new building foundations.
- Continue waterproofing of new foundation walls.
- Begin to pour slab on grade for lowest level of new building.
- Complete landscape and hardscape restoration of site around Harris Theatre.
- Procurement of materials for full-scale building envelop mock up.
Utility Infrastructure Project
Week of June 3:
- Substantially complete site restoration in Phase 2A (Music/Theater) areas.
- Complete trench back-fill in Phase 1B (Johnson Center South Plaza) areas.
- Continue site restoration in Phase 1A (Aquia Creek Lane), 1B east and 2B (West Building) areas.
- Continue hardscape and landscape restoration in Phase 1 (Aquia Creek Lane, Johnson Center South Plaza, EagleBank Arena) and 2 (Music/Theater, West Building) areas.
- Continue to re-install site lighting in Phase 1 and 2 areas.
- Continue trenching and pipe installation in Phase 3 areas (Wilkins Plaza extension from clock site to Southside Plaza).
- Complete fencing and soil and erosion control measures in Phase 4 areas (Southside east to Central Heating and Cooling Plant).
- Complete fencing and soil and erosion control measures in Phase 6 areas (near Commonwealth and Dominion Halls).
Week of June 10:
- Continue site restoration in Phase 1A (Aquia Creek Lane), 1B (Johnson Center South Plaza), and 2B (West Building) areas.
- Continue hardscape and landscape restoration in Phase 1 (Aquia Creek Lane, Johnson Center South Plaza, EagleBank Arena) and 2 (Music/Theater, West Building) areas.
- Continue to re-install site lighting in Phase 1 and 2 areas.
- Continue trenching and pipe installation in Phase 3 areas (Wilkins Plaza extension from clock site to Southside Plaza).
- Start trenching in Phase 4 areas (Southside east to Central Heating and Cooling Plant).
- Start trenching in Phase 6 areas (near Commonwealth and Dominion Halls).