Core Campus Project: Two-Week Planner, June 3–14

Robinson Hall Replacement

Week of June 3:

  • Continue excavation for foundations and underground mechanical work.
  • Continue to pour concrete at new building foundations.
  • Begin waterproofing of new foundation walls.
  • Continue landscape and hardscape restoration of site around Harris Theatre.
  • Commissioning and training for new mechanical equipment in Harris Theatre service/utility area.
  • Procurement of materials for full-scale building envelop mock up.

Week of June 10:

  • Continue excavation for foundations and underground mechanical work.
  • Continue to pour concrete at new building foundations.
  • Continue waterproofing of new foundation walls.
  • Begin to pour slab on grade for lowest level of new building.
  • Complete landscape and hardscape restoration of site around Harris Theatre.
  • Procurement of materials for full-scale building envelop mock up.

Utility Infrastructure Project

Week of June 3:

  • Substantially complete site restoration in Phase 2A (Music/Theater) areas.
  • Complete trench back-fill in Phase 1B (Johnson Center South Plaza) areas.
  • Continue site restoration in Phase 1A (Aquia Creek Lane), 1B east and 2B (West Building) areas.
  • Continue hardscape and landscape restoration in Phase 1 (Aquia Creek Lane, Johnson Center South Plaza, EagleBank Arena) and 2 (Music/Theater, West Building) areas.
  • Continue to re-install site lighting in Phase 1 and 2 areas.
  • Continue trenching and pipe installation in Phase 3 areas (Wilkins Plaza extension from clock site to Southside Plaza).
  • Complete fencing and soil and erosion control measures in Phase 4 areas (Southside east to Central Heating and Cooling Plant).
  • Complete fencing and soil and erosion control measures in Phase 6 areas (near Commonwealth and Dominion Halls).

Week of June 10:

  • Continue site restoration in Phase 1A (Aquia Creek Lane), 1B (Johnson Center South Plaza), and 2B (West Building) areas.
  • Continue hardscape and landscape restoration in Phase 1 (Aquia Creek Lane, Johnson Center South Plaza, EagleBank Arena) and 2 (Music/Theater, West Building) areas.
  • Continue to re-install site lighting in Phase 1 and 2 areas.
  • Continue trenching and pipe installation in Phase 3 areas (Wilkins Plaza extension from clock site to Southside Plaza).
  • Start trenching in Phase 4 areas (Southside east to Central Heating and Cooling Plant).
  • Start trenching in Phase 6 areas (near Commonwealth and Dominion Halls).