Core Campus Project: Two-Week Planner, April 8–19

Two-week look-ahead, Weeks of April 8, 15

Robinson Hall replacement

Week of April 8:

  • Finalize mass excavation activities.
  • Finalize testing of high temperature hot water and chilled water utilities to Harris Theatre, backfill chilled water trench.
  • Begin trenching and installation of storm water line on south east side of Harris Theatre.
  • Continue start up and testing of mechanical equipment in Harris Theatre service/utility area.
  • Finalize relocation of utilities on the site of Robinson A including chilled water pipes and storm water piping.
  • Finalize exterior enclosure on Robinson B.

Week of April 15:

  • Begin excavation for foundations and underground mechanical work.
  • Begin landscape and hardscape restoration of site around Harris Theatre.
  • Begin Installation of storm water line on southeast side of Harris Theatre.
  • Training for new Mechanical Equipment in Harris Theatre service/utility area.
  • Continue installation of storm water pipe at Harris Theatre area.
     

Utility Infrastructure Project

Week of April 8:

  • Backfill to continue in Phases 1A (Aquia Creek Lane), 1B (Johnson Center South Plaza) and 2B (West Building) areas.
  • Testing in phase 1A, 1B and 2B areas.
  • Continue backfill and site restoration in Phase 1A, 1B, 2A (Music Theater) and 2B areas.
  • Continue hardscape and landscape restoration in Phase 1 (Aquia Creek Lane, Johnson Center South Plaza, EagleBank Arena) and 2 (Music Theater, West Building) areas.
  • Continue to re-install site lighting in Phase 1 and 2 areas
  • Continue trenching and pipe installation in Phase 3 areas (Wilkins Plaza extension - from clock to Southside Plaza).
  • Existing utility locating to continue in Phase 4 areas (Southside east to central heating and cooling plant).

Week of April 15:

  • Backfill to continue in Phases 1A (Aquia Creek Lane) and 1B (Johnson Center South Plaza) areas.
  • Testing in phase 1A and 1B. 
  • Continue backfill and site restoration in Phase 1A, 1B, 2A (Music Theater) and 2B (West Building) areas.
  • Continue hardscape and landscape restoration in Phase 1 (Aquia Creek Lane, Johnson Center South Plaza, EagleBank Arena) and 2 (Music Theater, West Building) areas.
  • Continue to re-install site lighting in Phase 1 and 2 areas.
  • Continue trenching and pipe installation in Phase 3 areas (Wilkins Plaza extension - from Clock to Southside Plaza).
  • Existing utility locating to continue in Phase 4 areas (Southside east to Central Heating and Cooling Plant).