Core Campus Project: Two-Week Planner, April 22 to May 3

Robinson Hall Replacement

Week of April 22:

  • Continue excavation for foundations and underground mechanical work.
  • Begin to pour concrete at new building foundations.
  • Continue landscape and hardscape restoration of site around Harris Theatre.
  • Continue installation of storm water line on south east side of Harris Theatre.
  • Commissioning and training for new Mechanical Equipment in Harris Theatre service/utility area.

Week of April 29:

  • Continue excavation for foundations and underground mechanical work.
  • Continue to pour concrete at new building foundations.
  • Continue landscape and hardscape restoration of site around Harris Theatre.
  • Continue installation of storm water line on south east side of Harris Theatre.
  • Commissioning and training for new Mechanical Equipment in Harris Theatre service/utility area.

Utility Infrastructure Project

Week of April 22:

  • Testing and final tie-ins at phase 1A (Aquia Creek Lane) and 1B (Johnson Center South Plaza) areas.
  • Continue backfill and site restoration in Phase 1A, 1B, 2A (Music/Theater) and 2B (West Building) areas.
  • Continue hardscape and landscape restoration in Phase 1 (Aquia Creek Lane, Johnson Center South Plaza, EagleBank Arena) and 2 (Music/Theater, West Building) areas.
  • Continue to re-install site lighting in Phase 1 and 2 areas.
  • Continue trenching and pipe installation in Phase 3 areas (Wilkins Plaza extension, from Clock to Southside Plaza).
  • Existing utility locating to continue in Phase 4 areas (Southside east to Central Heating and Cooling Plant).

Week of April 29:

  • Testing in phase 1A (Aquia Creek Lane) and 1B (Johnson Center South Plaza).
  • Continue backfill and site restoration in Phase 1A, 1B, 2A (Music/Theater) and 2B (West Building) areas.
  • Continue hardscape and landscape restoration in phase 1 (Aquia Creek Lane, Johnson Center South Plaza, EagleBank Arena) and 2 (Music/Theater, West Building) areas.
  • Continue to re-install site lighting in Phase 1 and 2 areas.
  • Continue trenching and pipe installation in Phase 3 areas (Wilkins Plaza extension from Clock to Southside Plaza).
  • Existing utility locating to continue in Phase 4 areas (Southside east to Central Heating and Cooling Plant).