Core Campus Project: Two-Week Planner, March 25 to April 5

Robinson Hall Replacement

Week of March 25:

  • Install sheeting and shoring tiebacks and continue mass excavation activities.
  • Begin testing of high temperature hot water and chilled water utilities to Harris Theatre.
  • Begin start-up and testing of mechanical equipment in Harris Theatre service/utility area.
  • Continue to finalize relocation of utilities on the site of Robinson A including chilled water pipes, telecom, and storm water piping.
  • Continue to install exterior enclosure on Robinson B.

Week of April 1:

  • Install sheeting and shoring tiebacks and continue mass excavation activities.
  • Continue testing of high temperature hot water and chilled water utilities to Harris Theatre.
  • Continue start-up and testing of mechanical equipment in Harris Theatre service/utility area.
  • Continue to finalize relocation of utilities on the site of Robinson A including chilled water pipes and storm water piping.
  • Continue to install exterior enclosure on Robinson B.

Utility Infrastructure Project

Week of March 25:

  • Pipe installation and backfill to continue in Phases 1A (Aquia Creek Lane), 1B (Johnson Center South Plaza) and 2B (West Building) areas.
  • Testing in phase 1A and 1B areas.
  • Continue backfill and site restoration in Phase 1A, 1B and 2A (Music Theater) areas.
  • Continue hardscape and landscape restoration in phase 1A and 1B areas
  • Continue to re-install site lighting in Phase 1 (Aquia Creek Lane, Johnson Center South Plaza, EagleBank Arena) and 2A areas.
  • Continue trenching and pipe installation in Phase 3 areas (Wilkins Plaza extension - from Clock to Southside Plaza).
  • Planned outage (March 25-27) for Krug, Finley, West and East buildings to tie in new chilled water feed.

Week of April 1:

  • Backfill to continue in Phases 1A (Aquia Creek Lane), 1B (Johnson Center South Plaza) and 2B (West Building) areas.
  • Testing in phase 1A, 1B and 2B areas.
  • Continue backfill and site restoration in Phase 1A, 1B, 2A (Music Theater) and 2B areas.
  • Continue hardscape and landscape restoration in Phase 1 (Aquia Creek Lane, Johnson Center South Plaza, EagleBank Arena) and Phase 2 (Music Theater, West Building) areas.
  • Continue to re-install site lighting in Phase 1 and Phase 2 areas.
  • Continue trenching and pipe installation in Phase 3 areas (Wilkins Plaza extension - from Clock to Southside Plaza).