Robinson Hall Replacement
Week of March 25:
- Install sheeting and shoring tiebacks and continue mass excavation activities.
- Begin testing of high temperature hot water and chilled water utilities to Harris Theatre.
- Begin start-up and testing of mechanical equipment in Harris Theatre service/utility area.
- Continue to finalize relocation of utilities on the site of Robinson A including chilled water pipes, telecom, and storm water piping.
- Continue to install exterior enclosure on Robinson B.
Week of April 1:
- Install sheeting and shoring tiebacks and continue mass excavation activities.
- Continue testing of high temperature hot water and chilled water utilities to Harris Theatre.
- Continue start-up and testing of mechanical equipment in Harris Theatre service/utility area.
- Continue to finalize relocation of utilities on the site of Robinson A including chilled water pipes and storm water piping.
- Continue to install exterior enclosure on Robinson B.
Utility Infrastructure Project
Week of March 25:
- Pipe installation and backfill to continue in Phases 1A (Aquia Creek Lane), 1B (Johnson Center South Plaza) and 2B (West Building) areas.
- Testing in phase 1A and 1B areas.
- Continue backfill and site restoration in Phase 1A, 1B and 2A (Music Theater) areas.
- Continue hardscape and landscape restoration in phase 1A and 1B areas
- Continue to re-install site lighting in Phase 1 (Aquia Creek Lane, Johnson Center South Plaza, EagleBank Arena) and 2A areas.
- Continue trenching and pipe installation in Phase 3 areas (Wilkins Plaza extension - from Clock to Southside Plaza).
- Planned outage (March 25-27) for Krug, Finley, West and East buildings to tie in new chilled water feed.
Week of April 1:
- Backfill to continue in Phases 1A (Aquia Creek Lane), 1B (Johnson Center South Plaza) and 2B (West Building) areas.
- Testing in phase 1A, 1B and 2B areas.
- Continue backfill and site restoration in Phase 1A, 1B, 2A (Music Theater) and 2B areas.
- Continue hardscape and landscape restoration in Phase 1 (Aquia Creek Lane, Johnson Center South Plaza, EagleBank Arena) and Phase 2 (Music Theater, West Building) areas.
- Continue to re-install site lighting in Phase 1 and Phase 2 areas.
- Continue trenching and pipe installation in Phase 3 areas (Wilkins Plaza extension - from Clock to Southside Plaza).