Core Campus Project: Two-Week Planner, March 11–22

Robinson Hall Replacement

Week of March 11:

  • Continue sheeting, shoring and excavation activities.
  • Continue installation of high temperature hot water and chilled water utilities to Harris Theatre.
  • Continue interior improvements in Harris Theatre service/utility area.
  • Continue relocation of utilities on the site of Robinson A including chilled water pipes, telecom, and storm water piping.
  • Continue to install exterior enclosure on Robinson B.
  • Planned domestic Water outage for Harris Theater and Robinson B to tie in new water system.

Week of March 18:

  • Finalize sheeting, shoring and begin mass excavation activities.
  • Finalize installation of high temperature hot water and chilled water utilities to Harris Theatre.
  • Finalize interior improvements in Harris Theatre service/utility area.
  • Finalize relocation of utilities on the site of Robinson A including chilled water pipes, telecom, and storm water piping.
  • Continue to install exterior enclosure on Robinson B.

Utility Infrastructure project

Week of March 11:

  • Pipe installation and backfill to continue in Phases 1A (Aquia Creek Lane), 1B (Johnson Center South Plaza and 2B (West Building) areas.
  • Testing in phase 1A and 1B areas.
  • Continue backfill and site restoration in Phase 2A (Music Theater) areas.
  • Continue hardscape and landscape restoration in phase 1A and 1B areas.
  • Continue to re-install site lighting in Phase 1 (Aquia Creek Lane, Johnson Center South Plaza, EagleBank Arena) and 2A areas.
  • Planned chilled water outage of Fenwick Library to tie in new chilled water system equipment - outage planned from March 11-13.
  • Begin trenching and pipe installation in Phase 3 areas (Wilkins Plaza extension - from Clock to Southside Plaza).
  • Removal of willow oak trees on north and south sides of Wilkins Plaza.
  • Test pitting of existing conditions continues in Phase 4 area from Central Heating and Cooling Plant and west toward Southside up Rivanna River Lane.

Week of March 18:

  • Pipe installation and backfill to continue in Phases 1A (Aquia Creek Lane), 1B (Johnson Center South Plaza) and 2B (West Building) areas.
  • Testing in phase 1A and 1B areas
  • Continue backfill and site restoration in Phase 2A (Music Theater) areas.
  • Continue hardscape and landscape restoration in Phase 1A and 1B areas
  • Continue to re-install site lighting in Phase 1 (Aquia Creek Lane, Johnson Center South Plaza, EagleBank Arena) and 2A areas
  • Begin trenching and pipe installation in Phase 3 areas (Wilkins Plaza extension - from Clock to Southside Plaza).