Robinson Hall Replacement
Week of March 11:
- Continue sheeting, shoring and excavation activities.
- Continue installation of high temperature hot water and chilled water utilities to Harris Theatre.
- Continue interior improvements in Harris Theatre service/utility area.
- Continue relocation of utilities on the site of Robinson A including chilled water pipes, telecom, and storm water piping.
- Continue to install exterior enclosure on Robinson B.
- Planned domestic Water outage for Harris Theater and Robinson B to tie in new water system.
Week of March 18:
- Finalize sheeting, shoring and begin mass excavation activities.
- Finalize installation of high temperature hot water and chilled water utilities to Harris Theatre.
- Finalize interior improvements in Harris Theatre service/utility area.
- Finalize relocation of utilities on the site of Robinson A including chilled water pipes, telecom, and storm water piping.
- Continue to install exterior enclosure on Robinson B.
Utility Infrastructure project
Week of March 11:
- Pipe installation and backfill to continue in Phases 1A (Aquia Creek Lane), 1B (Johnson Center South Plaza and 2B (West Building) areas.
- Testing in phase 1A and 1B areas.
- Continue backfill and site restoration in Phase 2A (Music Theater) areas.
- Continue hardscape and landscape restoration in phase 1A and 1B areas.
- Continue to re-install site lighting in Phase 1 (Aquia Creek Lane, Johnson Center South Plaza, EagleBank Arena) and 2A areas.
- Planned chilled water outage of Fenwick Library to tie in new chilled water system equipment - outage planned from March 11-13.
- Begin trenching and pipe installation in Phase 3 areas (Wilkins Plaza extension - from Clock to Southside Plaza).
- Removal of willow oak trees on north and south sides of Wilkins Plaza.
- Test pitting of existing conditions continues in Phase 4 area from Central Heating and Cooling Plant and west toward Southside up Rivanna River Lane.
Week of March 18:
- Pipe installation and backfill to continue in Phases 1A (Aquia Creek Lane), 1B (Johnson Center South Plaza) and 2B (West Building) areas.
- Testing in phase 1A and 1B areas
- Continue backfill and site restoration in Phase 2A (Music Theater) areas.
- Continue hardscape and landscape restoration in Phase 1A and 1B areas
- Continue to re-install site lighting in Phase 1 (Aquia Creek Lane, Johnson Center South Plaza, EagleBank Arena) and 2A areas
- Begin trenching and pipe installation in Phase 3 areas (Wilkins Plaza extension - from Clock to Southside Plaza).