Robinson Hall Replacement
Week of February 25:
- Begin sheeting, shoring and excavation activities.
- Continue installation of high temperature hot water and chilled water utilities to Harris Theatre.
- Continue interior improvements in Harris Theatre service/utility area.
- Continue relocation of utilities on the site of Robinson A.
- Continue to install exterior enclosure on Robinson B after Robinson A is removed.
Week of March 4:
- Continue sheeting, shoring and excavation activities.
- Continue installation of high temperature hot water and chilled water utilities to Harris Theatre.
- Continue interior improvements in Harris Theatre service/utility area.
- Continue relocation of utilities on the site of Robinson A.
- Continue to install exterior enclosure on Robinson B after Robinson A is removed.
Utility Infrastructure Product
Week of February 25:
- Pipe installation and backfill to continue in Phase 1A (Aquia Creek Lane), 1B (Johnson Center South Plaza) and 2B (West Building) areas.
- Testing in phase 1A and 1B areas.
- Continue backfill and site restoration in Phase 2A areas.
- Continue hardscape and landscape restoration in phase 1A and 1B areas.
- Continue to re-install site lighting in Phase 1 (Aquia Creek Lane, Johnson Center South Plaza, EagleBank Arena) and 2A (Music Theater) areas.
- Begin trenching and pipe installation in Phase 3 areas (Wilkins Plaza extension - from Clock to Southside Plaza).
- Complete second outage for permanent tie in to Aquia Building. Planned outage for Aquia Building, Fenwick Towers, MIX and SUB I.
Week of March 4:
- Pipe installation and backfill to continue in Phase 1A (Aquia Creek Lane), 1B (Johnson Center South Plaza) and 2B (West Building) areas.
- Testing in phase 1A and 1B areas.
- Continue backfill and site restoration in Phase 2A (Music Theater) areas.
- Continue hardscape and landscape restoration in Phase 1A and 1B areas.
- Continue to re-install site lighting in Phase 1 (Aquia Creek Lane, Johnson Center South Plaza, EagleBank Arena) and 2A areas.
- Begin trenching and pipe installation in Phase 3 areas (Wilkins Plaza extension - from Clock to Southside Plaza).