About this Planner:
The following is a list of planned activities taking place over the next two weeks in the Core Campus Project.
For more information, please visit construction.gmu.edu
Robinson Hall Replacement
Week of October 15:
- Continue construction of firewalls in Robinson B
- Continue interior improvements in Harris Theatre service/utility area
- Continue installation of new utilities to Harris Theatre
- Trenching for electric duct bank behind Harris Theatre
- Pour concrete for column shoring at Robinson B
Week of October 22:
- Continue construction of firewalls in Robinson B
- Continue interior improvements in Harris Theatre service/utility area
- Continue installation of new utilities to Harris Theatre
- Trench and install electric feeders to new fire pump room in Harris Theatre
- Place steel columns for shoring at Robinson B
Utility Infrastructure Project
Week of October 15:
- Trenching and pipe installation continues in all Phase 1 areas (Aquia Creek Lane North, Johnson Center South Plaza, EagleBank Arena)
- Install and test piping in Phase 1 areas
- Begin backfill of chilled water supply and return pipe trenches in all Phase 1 areas
- Cross Aquia Creek Lane with pipe trench excavations
Week of October 22:
- Trenching and pipe installation continues in all Phase 1 areas (Aquia Creek Lane North, Johnson Center South Plaza, EagleBank Arena)
- Install and test piping in Phase 1 areas
- Begin backfill of chilled water supply and return pipe trenches in all Phase 1 areas