Core Campus Project: Two-Week Planner - October 15 - October 28

About this Planner:

The following is a list of planned activities taking place over the next two weeks in the Core Campus Project. 

For more information, please visit construction.gmu.edu


Robinson Hall Replacement

Week of October 15:

  • Continue construction of firewalls in Robinson B
  • Continue interior improvements in Harris Theatre service/utility area
  • Continue installation of new utilities to Harris Theatre
  • Trenching for electric duct bank behind Harris Theatre
  • Pour concrete for column shoring at Robinson B

Week of October 22:

  • Continue construction of firewalls in Robinson B
  • Continue interior improvements in Harris Theatre service/utility area
  • Continue installation of new utilities to Harris Theatre
  • Trench and install electric feeders to new fire pump room in Harris Theatre
  • Place steel columns for shoring at Robinson B

Utility Infrastructure Project

Week of October 15:

  • Trenching and pipe installation continues in all Phase 1 areas (Aquia Creek Lane North, Johnson Center South Plaza, EagleBank Arena)
  • Install and test piping in Phase 1 areas
  • Begin backfill of chilled water supply and return pipe trenches in all Phase 1 areas
  • Cross Aquia Creek Lane with pipe trench excavations

Week of October 22:

  • Trenching and pipe installation continues in all Phase 1 areas (Aquia Creek Lane North, Johnson Center South Plaza, EagleBank Arena)
  • Install and test piping in Phase 1 areas
  • Begin backfill of chilled water supply and return pipe trenches in all Phase 1 areas