About this Planner
The following is a list of planned activities taking place over the next two weeks in the Core Campus Project.
For more information, please visit construction.gmu.edu
Robinson Hall Replacement
Week of September 17:
- Hazardous materials abatement to be complete in Robinson A by September 21.
- Start installation of construction site entrance between Harris Theatre and SUB I loading dock area.
Week of September 24:
- Begin demolition of building site areas.
- Mobilize and investigate existing conditions in Robinson B and Harris Theatre.
- Marking of existing underground utilities.
Utility Infrastructure Project
Week of September 17:
- Receive Phase 1 piping and place in laydown areas.
- Trenching and pipe installation continues in all Phase 1 areas (Aquia Creek Lane North, Johnson Center South Plaza, EagleBank Arena).
Week of September 24:
- Trenching and pipe installation continues in all phase 1 areas (Aquia Creek Lane North, Johnson Center South Plaza, EagleBank Arena).
- Planned outage at EagleBank Arena to tie in new chilled water supply and return piping.