Core Campus Project: Two-Week Planner - September 17- September 30

About this Planner

The following is a list of planned activities taking place over the next two weeks in the Core Campus Project. 

For more information, please visit construction.gmu.edu

Robinson Hall Replacement

Week of September 17:

  • Hazardous materials abatement to be complete in Robinson A by September 21. 
  • Start installation of construction site entrance between Harris Theatre and SUB I loading dock area. 

Week of September 24:

  • Begin demolition of building site areas.
  • Mobilize and investigate existing conditions in Robinson B and Harris Theatre.
  • Marking of existing underground utilities.

Utility Infrastructure Project

Week of September 17:

  • Receive Phase 1 piping and place in laydown areas.
  • Trenching and pipe installation continues in all Phase 1 areas (Aquia Creek Lane North, Johnson Center South Plaza, EagleBank Arena).

Week of September 24:

  • Trenching and pipe installation continues in all phase 1 areas (Aquia Creek Lane North, Johnson Center South Plaza, EagleBank Arena).
  • Planned outage at EagleBank Arena to tie in new chilled water supply and return piping.