The following is a list of planned activities taking place over the next two weeks in the Core Campus Project.
For more information, please visit construction.gmu.edu
Robinson Hall Replacement
Week of September 3:
- Hazardous materials abatement in Robinson A continues.
- Start installation of erosion and sediment control measures at the Robinson Hall Replacement construction site.
Week of September 10:
- Hazardous materials abatement in Robinson A to be completed by September 14.
- Complete installation of erosion and sediment control measures.
- Installation of temporary pedestrian pathways around the Robinson Hall replacement construction site.
Utility Infrastructure Project:
Week of September 3:
- Complete demolition of existing sidewalks in Phase 1A areas (Aquia Creek Lane North) and Phase 1C (near EagleBank Arena).
- Complete removal of existing curb, gutter and pavement sections in all Phase 1 areas (Aquia Creek Lane North, Johnson Center South Plaza, near EagleBank Arena).
- Remove existing pavement section and trenching to begin in all Phase 1 areas.
Week of September 10:
- Trenching and pipe installation continues in all Phase 1 areas (Aquia Creek Lane, Johnson Center South Plaza, EagleBank Arena).