Core Campus Project: Two Week Planner - September 3 through September 16

The following is a list of planned activities taking place over the next two weeks in the Core Campus Project. 

For more information, please visit construction.gmu.edu

Robinson Hall Replacement
Week of September 3:
  • Hazardous materials abatement in Robinson A continues.
  • Start installation of erosion and sediment control measures at the Robinson Hall Replacement construction site.
Week of September 10:
  • Hazardous materials abatement in Robinson A to be completed by September 14.
  • Complete installation of erosion and sediment control measures.
  • Installation of temporary pedestrian pathways around the Robinson Hall replacement construction site.
Utility Infrastructure Project:
Week of September 3:
  • Complete demolition of existing sidewalks in Phase 1A areas (Aquia Creek Lane North) and Phase 1C (near EagleBank Arena).
  • Complete removal of existing curb, gutter and pavement sections in all Phase 1 areas (Aquia Creek Lane North, Johnson Center South Plaza, near EagleBank Arena).
  • Remove existing pavement section and trenching to begin in all Phase 1 areas. 
Week of September 10:
  • Trenching and pipe installation continues in all Phase 1 areas (Aquia Creek Lane, Johnson Center South Plaza, EagleBank Arena).