Core Campus Project: Two Week Planner - August 27- Sept 9

About this Planner

The following is a list of planned activities taking place over the next two weeks in the Core Campus Project. 

For more information, please visit construction.gmu.edu


Robinson Hall Replacement

Week of August 27:

  • Hazardous material abatement in Robinson A continues.
  • Complete any outstanding items for Firewall patching in Robinson B.

Week of September 3:

  • Hazardous materials abatement in Robinson A continues.
  • Start installation of erosion and sediment control measures at the Robinson Hall Replacement construction site.

Utility Infrastructure Project

Week of August 27:

  • Continue demolition of existing sidewalks in Phase 1 areas of Aquia Creek Lane.
  • Continue removal of existing curb, gutter and pavement sections in all Phase 1 areas (Aquia Creek Lane, Johnson Center South Plaza, near EagleBank Arena.

Week of September 3:

  • Complete demolition of existing sidewalks in Phase 1A areas (Aquia Creek Lane North) and Phase 1C (near EagleBank Arena).
  • Complete removal of existing curb, gutter and pavement sections in all Phase 1 areas (Aquia Creek Lane North, Johnson Center South Plaza, near EagleBank Arena).
  • Remove existing pavement section and trenching to begin in all Phase 1 areas.