About this Planner
The following is a list of planned activities taking place over the next two weeks in the Core Campus Project.
For more information, please visit construction.gmu.edu
Robinson Hall Replacement
Week of August 20:
- Firewall patching in Robinson B is scheduled for completion by August 24
- Hazardous materials abatement in Robinson A continues
- Tree removal scheduled completion by August 20.
Week of August 27
- Hazardous material abatement in Robinson A continues.
- Complete any outstanding items for Firewall patching in Robinson B.
Utility Infrastructure Project
Week of August 20:
- Complete install of temporary asphalt paths in phase 1 areas (North Loop/Aquia Creek Lane; Johnson Center South Plaza; EagleBank Arena).
- Continue removal of curb, gutter and pavement sections within Phase 1 areas.
- Continue installing erosion and sediment control measures in Phase 1 areas.
- Removing trees and vegetation in Phase 1 areas.
- Salvage remove and protect existing light poles to be re-installed at completion of work in Phase 1 areas.
Week of August 27:
- Continue demolition of existing sidewalks in Phase 1 areas of Aquia Creek Lane.
- Continue removal of existing curb, gutter and pavement sections in all Phase 1 areas.
- Complete installation of temporary lighting in all Phase 1 areas.