Core Campus Project: Two-Week Planner - August 20 to September 2

About this Planner

The following is a list of planned activities taking place over the next two weeks in the Core Campus Project. 

For more information, please visit construction.gmu.edu


Robinson Hall Replacement

Week of August 20:

  • Firewall patching in Robinson B is scheduled for completion by August 24
  • Hazardous materials abatement in Robinson A continues
  • Tree removal scheduled completion by August 20.

Week of August 27

  • Hazardous material abatement in Robinson A continues.
  • Complete any outstanding items for Firewall patching in Robinson B.

 
 
Utility Infrastructure Project

Week of August 20:

  • Complete install of temporary asphalt paths in phase 1 areas (North Loop/Aquia Creek Lane; Johnson Center South Plaza; EagleBank Arena).
  • Continue removal of curb, gutter and pavement sections within Phase 1 areas.
  • Continue installing erosion and sediment control measures in Phase 1 areas.
  • Removing trees and vegetation in Phase 1 areas.
  • Salvage remove and protect existing light poles to be re-installed at completion of work in Phase 1 areas.

Week of August 27:

  • Continue demolition of existing sidewalks in Phase 1 areas of Aquia Creek Lane.
  • Continue removal of existing curb, gutter and pavement sections in all Phase 1 areas.
  • Complete installation of temporary lighting in all Phase 1 areas.