New Academic Building Project
Week of August 6:
- Firewall patching continues in Robinson B, second floor.
- Tree removal on north, east and west sides of Robinson A, begins August 8.
- Hazardous materials abatement in Robinson A, begins August 9.
- Installation of construction signs and banners.
- Installation of wayfinding and sidewalk detour signs.
Week of August 13:
- Firewall patching continues in Robinson B, first floor.
- Tree removal continues around Robinson A.
- Hazardous materials abatement continues in Robinson A.
Utility Infrastructure Project
Week of August 6:
- Complete test pitting for existing utilities that might be in pipe paths.
- Removal and salvaging of existing site fixtures in Phase 1 areas (north loop next to Thompson Hall, south of the Johnson Center, Patriot Circle near EagleBank Arena).
- Install temporary lighting in Phase 1 areas.
- Remove existing curbs and gutters south of Johnson Center.
Week of August 13:
- Complete removal of curb, gutter and pavement sections in Phase 1 areas.
- Begin trenching for chilled water supply and return piping installation in Phase 1 areas.
For more information on the Core Campus Project, visit construction.gmu.edu.